Biomass blunders

Typical mistakes made by new wood biomass heating projects

Over the past 10 years the development of biomass heating projects has increased significantly. The Northeast United States led the way, motivated by replacing fossil fuels with biomass in public buildings. Biomass Resource Energy Center (BERC) has been at the forefront of promoting the push towards biomass heating.

As in any new technology adoption, mistakes were bound to happen. Over the 10 years of biomass heating development in North America, I witnessed many mistakes that often led to project failure. Here are some of the typical mistakes I see.

CART BEFORE THE HORSE

It is surprising how many projects do not go through a fuel supply due diligence process. Wood fuel is the largest variable cost of each biomass heating project. In some regions, wood fuel price and quality can often fluctuate significantly. Many biomass heating projects are built without concern for that fluctuation. This leads to some projects stopping operations for certain periods of time, and some to revert to heating oil or natural gas.

VERY FEW TO NO BIDS

Many biomass heating project developers think that once a project is built, suppliers will come rushing through the door. This is certainly not my experience. I have seen projects where my company was the only bidder, or where there were no bidders at all. This is because sawmill owners and loggers typically do not spend much time online searching for RFPs and RFQs, especially in areas where biomass heating projects are rare. Successful projects directly source out all the potential wood fibre suppliers, notifying them about the bidding process.

BIOMASS TERMINOLOGY

Tree chip, paper chip, clean chip, fuel chip, bole wood chip – all those terms can mean the same or different things. Wood biomass terms are not standardized, and therefore the same terms can have different meanings in different regions. The best way to avoid mistakes in terminology is to visit the supplier site and examine the fuel product before signing a contract. Otherwise, a biomass heating project runs a risk of contracting fuel that is not compatible with its equipment.

TECHNOLOGY ADAPTATION

Biomass heating projects are more successful if the technology adapts to the market’s feedstock, and not the other way around. For example, a project in northern Pennsylvania installed a boiler that accepted feedstock with moisture content (MC) lower than 15 per cent, based on what was available from a sawmill next door. However, that sawmill eventually shut down, and the biomass project could not find other suppliers in the woodshed that could supply material lower than 15 per cent MC. Prior to deciding on technology, each biomass heating project should clearly understand the type of wood fuel available in the market.

FUEL STORAGE AND DISRUPTION PLANS

To operate smoothly without fuel supply disruptions depends on a geographical region. Weather affects logging and trucking operations, so regions with heavy snowfall are prone to fuel supply disruptions, and therefore projects located in those regions require larger storage capacity. Again, discussing these issues with suppliers directly is the best way to understand how big fuel storage capacity should be to mitigate against fuel supply disruptions.

Weather is just one potential cause of fuel supply disruption. Others include vendor default, equipment failure, and catastrophic event. A robust fuel supply disruption plan is necessary for each project to prevent surprises down the line. New biomass heating projects often lack such plans, leading to preventable shut downs. For example, biomass heating projects often rely on just one fuel vendor. If that vendor defaults, and there are no planned back-up vendors, then the project runs short of fuel. Having a good fuel supply disruption plan can easily prevent such situations.

PRE-CONSTRUCTION MISCOMMUNICATION

One of the common mistakes in the preconstruction phase of a biomass heating project is miscommunication between the construction project manager and plant operations manager. The project manager’s goal is to ensure that construction is completed on time and under budget, while the operations manager’s goal is to ensure that there is little to no downtime. Because these objectives are misaligned, miscommunication can be a problem down the line.

In one case, for example, the project manager purchased a cheap storage facility to stay under budget, without asking the operations manager for an opinion. Storage problems have caused significant downtime since the project became operational. Therefore, it is important for a project manager and the plant operations manager to engage in open communication to ensure the project is not compromised, for example, by potential budgetary savings.

There are many more potential mistakes that can happen when developing a biomass heating project. A comprehensive due diligence process is the only way to minimize the chance of potential failure. This is especially the case on the feedstock supply side of things. Fuel is an ongoing cost; therefore, making sure that all potential issues are weeded out prior to or during construction will save the variable costs associated with running a biomass heating project in the long-term.

Pat Liew is the business development manager for Ecostrat Inc. www.ecostrat.com

©Annex Biomass_CFI_OF. View All Articles.

Lessons Learned
https://magazine.canadianbiomassmagazine.ca/article/Lessons+Learned/3308127/568783/article.html

Menu
  • Page View
  • Contents View
  • Advertisers

Issue List

Summer 2025

Spring 2025

Winter 2025

Fall 2024

Summer 2024

Spring 2024

Winter 2024

Fall 2023

Summer 2023

Spring 2023

Winter 2023

Fall 2022

Summer 2022

Spring 2022

Winter 2022

Fall 2021

Summer 2021

Spring 2021

Winter 2021

Fall 2020

Summer 2020

Spring 2020

Winter 2020

Fall 2019

Summer 2019

Spring 2019

Winter 2019

September-October 2018

JulyAugust 2018

MayJune 2018

March April 2018

January-February 2018

November/December 2017

September/October 2017

July/August 2017

May-June 2017

March-April 2017

January February 2017

November December 2016

October 2016

July August 2016

June 2016

March April 2016

January February 2016

November/December 2015

September/October 2015

July August 2015

May-June 2015

March-April 2015

January-February 2015

November - December 2014

September October 2014

Intersaw Guide 2014

July August 2014

May June 2014

March/April 2014

January/February 2014

November/December 2013

September/October 2013

August/September 2013

May/June 2013

March/April 2013

January/February 2013

November/December 2012

September/October 2012

July/August 2012

May/June 2012

March/April 2012

January/February 2012

November/December 2011

September/October 2011

July/August 2011

May/June 2011

April 2011

January/February 2011

November/December 2010

September/October 2010

July/August 2010

May/June 2010

March/April 2010

January/February 2010

November/December 2009

September/October 2009

August 2009

June 2009

March 2009

December 2008

August 08


Library