Canadian Biomass - September/October 2015

In Progress

2015-10-05 05:16:05

RENTECH FACILITIES ENCOUNTER DELAYS

Rentech’s pellet plants in Atikokan, Ont. And Wawa, Ont. Have encountered delays in wood pellet production due to equipment failures and issues with material handling equipment.

“The Atikokan plant has been generating positive EBITDA since May,” stated Keith Forman, president and CEO of Rentech. “At Wawa, we are producing a limited quantity of pellets. We will need to modify and replace the log in-feed equipment and a signification portion of conveyance systems at the Wawa plant this fall and into next year, to address the construction flaws we discovered during ramp-up.”

WAWA FACILITY – Most of the equipment at the Wawa facility has been commissioned and the plant is producing a limited quantity of wood pellets. However, Rentech discovered that it needs to modify the front end system of the facility that handles logs and feeds them into the chipper, and modify or replace a significant portion of the conveyors that handle chips and pellets.

“These issues are preventing us from ramping up the plant to expected production levels,” the company stated. “We expect to correct these issues during this fall and the first half of next year. We currently estimate that correcting these problems will increase our total expected project spending for the Canadian pellet plants to approximately $145 million, which is $5 million above the high end of our previous guidance range of $131 million to $140 million.”

Rentech expects the Wawa Facility to be operating at full capacity by sometime in the second half of 2016.

ATIKOKAN FACILITY – The Atikokan facility has completed commissioning and is in the ramp-up phase. However, the facility experienced a transformer failure and has been temporarily using a smaller transformer that causes the facility to operate at reduced rates. Rentech plans to install a larger permanent transformer in the third quarter of 2015, which will allow Atikokan to operate at full rates.

During the ramp-up phase, Rentech identified the need to replace or repair the truck dump conveyor and hopper at the facility, and the need to modify some of the conveyors at the plant. Atikokan may still reach full capacity in February 2016; however, the timing could shift by several months depending on the degree of modifications needed to correct the material handling equipment issues and any other possible issues that may arise during ramp-up.

OKANAGAN PELLET COMPANY BEGINS PLANT UPGRADES

Viridis Energy Inc., recently announced that its whollyowned subsidiary, Okanagan Pellet Company Inc. (OPC), has commenced a major oneto two-year plant upgrade that will be conducted in three phases. The OPC plant upgrades are intended to address new regulatory requirements for safe storage and management of wood pellets and ensure the plant complies with the National Fire Protection Association and B.C. Fire Safety code.

The first phase is underway and will provide for a separation of the two main production lines, pellets and shavings, so they can be operated independently. This phase, which is expected to take eight to 10 weeks during which production will be suspended, also includes substantial improvements in the wood dust management system to ensure continued compliance with the increasingly stringent safety guidelines for the wood industry, implemented in British Columbia.

The second phase includes the addition of new, semi-permanent tent structures for the safe storage of wood fiber. The storage systems will substantially increase OPC’s fibre capacity and include the de-commissioning of the current storage building, improving production efficiencies. The third phase of the upgrades will include the addition of a new pellet press and state-of-the-art dryer that will expand the facility’s capacity by approximately 50 per cent. Planning for the third phase will begin in Q4 2015.

This will mark the first significant enhancements of OPC’s facility since the plant was acquired by Viridis in April 2010 and are expected to create midterm and long-term increases in revenue and profitability. In the short term, the company anticipates incurring a production shortfall of approximately 10,000 tons of pellet production; however, it is expected to have less of an impact on sales. OPC is covering its wood pellet delivery obligations through a combination of existing inventory and additional product acquisition via Viridis Merchants Inc. (VMI).

BIO-FUNDING

Alberta Innovates Bio Solutions (AI Bio) has launched a new funding program, “Alberta Bio Future, Research and Innovation,” aimed at advancing knowledge that accelerates growth of new bioindustrial products or bioindustrial technologies for the benefit of Albertans.

The ABF Research and Innovation program has a total $4.5 million in available funding. Project funding amounts will be determined on a case-by-case basis, depending on the quality and scope of the project. In addition to funding, AI Bio assists researchers and companies with advice and connections.

Researchers, companies or industry groups based in Alberta, and researchers conducting projects that benefit Alberta, are invited to apply by submitting a Letter of Intent.

The deadline is Oct. 28, 2015 at 4 p.m. MT. Eligibility requirements are available at bio.albertainnovates.ca.

©Annex Biomass_CFI_OF. View All Articles.

In Progress
https://magazine.canadianbiomassmagazine.ca/article/In+Progress/2288699/275455/article.html

Menu
  • Page View
  • Contents View
  • Advertisers

Issue List

Summer 2025

Spring 2025

Winter 2025

Fall 2024

Summer 2024

Spring 2024

Winter 2024

Fall 2023

Summer 2023

Spring 2023

Winter 2023

Fall 2022

Summer 2022

Spring 2022

Winter 2022

Fall 2021

Summer 2021

Spring 2021

Winter 2021

Fall 2020

Summer 2020

Spring 2020

Winter 2020

Fall 2019

Summer 2019

Spring 2019

Winter 2019

September-October 2018

JulyAugust 2018

MayJune 2018

March April 2018

January-February 2018

November/December 2017

September/October 2017

July/August 2017

May-June 2017

March-April 2017

January February 2017

November December 2016

October 2016

July August 2016

June 2016

March April 2016

January February 2016

November/December 2015

September/October 2015

July August 2015

May-June 2015

March-April 2015

January-February 2015

November - December 2014

September October 2014

Intersaw Guide 2014

July August 2014

May June 2014

March/April 2014

January/February 2014

November/December 2013

September/October 2013

August/September 2013

May/June 2013

March/April 2013

January/February 2013

November/December 2012

September/October 2012

July/August 2012

May/June 2012

March/April 2012

January/February 2012

November/December 2011

September/October 2011

July/August 2011

May/June 2011

April 2011

January/February 2011

November/December 2010

September/October 2010

July/August 2010

May/June 2010

March/April 2010

January/February 2010

November/December 2009

September/October 2009

August 2009

June 2009

March 2009

December 2008

August 08


Library