Canadian Biomass - March April 2016

Building Bioenergy

Andrew Snook 2016-03-25 04:33:02

Two new projects are building up B.C. grids with biomass

Woody biomass will be generating a lot of juice in the interior of British Columbia by the end of 2016.

Two biomass-fuelled power plants in the B.C. Interior will be generating a combined 80 megawatts of electricity that will be fed into BC Hydro’s grid. The 40MW biomass power plants are located in the southern interior in Merritt and in the northern interior in Fort St. James.

Both power plants will be fuelled by a combination of sawdust and other residuals collected from local sawmills, harvested dead wood and cleanup operations.Once commissioned, the power plants will have the capacity to supply electricity to upwards of 160,000 homes in the province, as well as reduce CO2 emissions for the province by 570,000 tonnes annually.

The two power plants are owned by Fengate Capital and Veolia with the turnkey construction contracted out to Spanish energy firm Iberdrola for $330 million for both power plants.

Enrique Reyes Molano, site manager for Iberdrola, says the decision to create the massive power plants was mainly to help plan and promote future growth in the Fort St. James and Merritt areas. He says the B.C. government is interested in using the electricity mainly to have the ability to grow its local economies, which are mainly fuelled by the forest sector in Merritt and the forestry and mining industries in Fort St. James.

The construction of the facilities has been a major boost to the local economies in Merritt and Fort St. James, supplying approximately 250 construction jobs to the towns, as well as 22 new direct jobs for the operation and maintenance of the plants.

Another major benefit of having the power plant up and running in Fort St. James is that it will create a home for much of the dead pine that is still sitting in local forests due to the mountain pine beetle epidemic that ravaged many of the forests in northern B.C.

“We’ve had increased harvesting of the forests but we’re going to see that drop off real soon,” says Emily Colombo, economic development officer for the Fort St. James District. “Because the dead wood standing in the forest loses merchantability year after year, it’s only good for harvesting and processing for a number of years. Even though there’s lots of dead wood in the forests, it’s no longer going to be desirable by the sawmill companies.So it’s great to have the Fort St. James green energy project starting up because it gives us a purpose for our waste wood.Until now it’s been burned in the bush… it’s just releasing carbon dioxide into the atmosphere.”

The construction of the Fort St. James plant is expected to be complete by November 2016 with the Merritt power plant coming online this December.

The main equipment installed for each project is a Siemens SST-400, 40MW condensing steam turbine; an FSE biomass boiler (307,260 PPH); a GC Power transformer (30/40/50 MVA, 65C Wye Delta); and an Emerson distributed control system (DCS).

FEEDING SYSTEMS

In Fort St. James, the boilers are fed woody biomass via three 6,560 m3 silos that can hold upwards of a 6.75-day supply for the plant. The fuel is supplied through the residuals from the local Confiex and Apollo Forest Products sawmills, as well as through local contractors harvesting local dead wood.

The fuel is received, weighed and off-loaded in a dedicated area. It is then screened and stored in the three concrete silos, which required 4,440 m3 of concrete and 570,000 kg of reinforced steel in their construction. All of the silos are equipped with a steel roof, are 11.6 metres in height and have a silo diameter of 25 metres.

In Merritt, the boilers are fed woody biomass via a large conveyor connected directly to Tolko’s sawmill located next to the power plant.

Each power plant will consume approximately 24 dry tonnes per hour of biomass with a total annual consumption of about 200,000 dry tonnes.

BOILERS AND TURBINES

Both locations feature a state-of-the-art grate, natural circulation biomass boiler supplied by FSE Energy. The flue gases heat the wall tubes of the combustion chambers and the water is partly evaporated.Water and steam rise through tubes back to the steam drum where the steam is separated from the water.

After leaving the steam drum, the saturated steam is transferred to the superheaters then is transferred into a Siemens SST-400, 40MW-condensing steam turbine.

Each Siemens generator is rated at 1,800 rpm and produces electricity at 13. 8 kV with each turbine rated at 5,143 rpm, producing upwards of 41.39MW of electricity that will be fed in BC Hydro’s grid.

OVERCOMING CHALLENGES

Montserrat Varas Roncero, project manager for Iberdrola’s Fort St. James and Merritt Biomasses Generation Division, says one of the toughest issues when starting work in a new country is learning all the ins and outs, including the logistical challenges of the project sites, as well as the various provincial, municipal and federal regulations and governmental processes.

Educating the local workforces on Iberdrola’s processes was another barrier to overcome.

“At the beginning, no one in Canada knew Iberdrola,” says Molano. “Now in British Columbia, in this industry, most of the construction companies know Iberdrola, how we work, and they are learning a lot about us.”

Working with the safety associations and government organizations created similar challenges for Iberdrola.

“At the very beginning it was hard to work with them – we spent a lot of time explaining to them who Iberdrola is, how we work, the kinds of contractors we use to develop these kinds of plants – but now we feel very comfortable with them,” Molano says. “The relationship is really good. They are working with us as a team very closely and this is giving us an opportunity to solve all the problems and issues in a very efficient manner.”

Despite all the hurdles and barriers Iberdrola has had to overcome, the two biomass-fuelled power plants should be commissioned on schedule in Fort St. James and Merritt, providing a foundation for the province to continue to grow the towns’ local economies and provide much-needed employment for both areas of the B.C. Interior. •

ENVIRONMENTAL IMPACT

Both power plants have set gaseous emissions guarantees.

The particulate matter is to be less than 20 mg/m3, Nox emissions less than 512 mg/m3 and carbon dioxide emissions less than 160 mg/m3.

Particulate matter at the boiler stacks is reduced through the installation of a high-efficiency electrostatic precipitator.

The bottom and fly ashes that will be left over from the process are stored and sold for use in other applications, such as the making of concrete (fly ash) or for spreading on local farmlands (bottom ash).

The near field noise for the main operating levels of the plant (areas of the plant with permanent or usual presence of workers during operation) are to be no more than 85 dB(A); with the far field noise produced exclusively by the plant at site boundary to be no greater than 65 dB(A).

The installation of air-cooling condensers (ACCs)at both facilities allow for the facilities to keep their water requirements to a minimum. Each facility is expected to have a water consumption level less than 90 litres per minute.

©Annex Biomass_CFI_OF. View All Articles.

Building Bioenergy
https://magazine.canadianbiomassmagazine.ca/article/Building+Bioenergy/2437797/295308/article.html

Menu
  • Page View
  • Contents View
  • Advertisers

Issue List

Summer 2025

Spring 2025

Winter 2025

Fall 2024

Summer 2024

Spring 2024

Winter 2024

Fall 2023

Summer 2023

Spring 2023

Winter 2023

Fall 2022

Summer 2022

Spring 2022

Winter 2022

Fall 2021

Summer 2021

Spring 2021

Winter 2021

Fall 2020

Summer 2020

Spring 2020

Winter 2020

Fall 2019

Summer 2019

Spring 2019

Winter 2019

September-October 2018

JulyAugust 2018

MayJune 2018

March April 2018

January-February 2018

November/December 2017

September/October 2017

July/August 2017

May-June 2017

March-April 2017

January February 2017

November December 2016

October 2016

July August 2016

June 2016

March April 2016

January February 2016

November/December 2015

September/October 2015

July August 2015

May-June 2015

March-April 2015

January-February 2015

November - December 2014

September October 2014

Intersaw Guide 2014

July August 2014

May June 2014

March/April 2014

January/February 2014

November/December 2013

September/October 2013

August/September 2013

May/June 2013

March/April 2013

January/February 2013

November/December 2012

September/October 2012

July/August 2012

May/June 2012

March/April 2012

January/February 2012

November/December 2011

September/October 2011

July/August 2011

May/June 2011

April 2011

January/February 2011

November/December 2010

September/October 2010

July/August 2010

May/June 2010

March/April 2010

January/February 2010

November/December 2009

September/October 2009

August 2009

June 2009

March 2009

December 2008

August 08


Library