Canadian Biomass - Summer 2024

Converting landfill gas to RNG in Edmonton

Jeannine Moyer 2024-08-02 07:58:50

The Clover Bar Landfill in Edmonton recovers landfill gas to generate renewable energy. The site has been recovering and converting the gas into electricity since 2005 and is currently early in the process of developing a new system to convert the gas produced from decomposing landfill organics into renewable natural gas (RNG) for injection into Alberta’s natural gas distribution system.

The overarching goals of the project are to increase the environmental sustainability and economic viability of the facility through the reduction of greenhouse gas (GHG) emissions. It will also help advance Edmonton towards its goal of being carbon neutral as a municipality by 2050. Initial project planning began in 2020 and work to scope, design and procure the project is underway.

The landfill gas produced by the Clover Bar Landfill is presently co-owned by the City of Edmonton and Capital Power. For 16 years, Capital Power has worked collaboratively with the City, managing the landfill gas collection system to produce electricity, retaining 100 per cent of the sale of electricity and sharing a portion of the GHG credits with the City. Project stakeholders include the City of Edmonton, Emissions Reductions Alberta and Capital Power, who is also the construction project manager. Capital Power would also invest in the eventual RNG conversion facility and would share the profits generated from the sale of the RNG and environmental credits produced.

Working to achieve the project goals of reducing GHG emissions while enhancing the environmental sustainability and economic viability of landfill gas management, the group has divided the scope of the project into three phases:

Phase 1: Landfill gas collection – replace and improve landfill gas collection and recovery system for the Clover Bar Landfill.

Phase 2: Upgrade landfill gas to RNG – improve collected landfill gas to pipeline quality natural gas.

Phase 3: Supply RNG to the natural gas network – inject RNG into the natural gas grid through interconnection piping.

LESSONS LEARNED SO FAR

While the transition from producing electricity to RNG from landfill gas is still in its early stages, project stakeholders have learned a few lessons along the way.

Lesson #1. The importance of synergizing private and public sector procurement and decision-making approaches

This RNG project relies on working with and combining various levels of government with private sector companies at every step of the way. Project managers learned early in the process the importance of engaging everyone in a productive manner, including prioritizing communications and establishing a streamlined decision- making process. A thorough understanding of regulations and trade implications, including competitive policies, free trade agreements and compliance requirements is essential to each partner.

Establishing a fair and transparent procurement process also needs to include significant input from every partner.

Lesson #2. Scoping of procurement to ensure operational efficiencies

When it comes to undertaking such a complex project, a firm understanding of the existing landfill is essential. In the case of the Clover Bar Landfill, having a high level of confidence and understanding of the landfill gas quality and composition is required. The project team has an advantage in this situation, having managed the landfill gas for the production of electricity. The team already has an intimate understanding of the importance of gas quality, or rather, the implications unknown gas quality can have on available technology options and final product output. That’s why they will be prioritizing a flexible design to incorporate a range of gas qualities and expandability as required. They have considered the operations and cost implications and as a result, have designed a collection system that has enough flexibility to fine-tune and optimize gas quality and flow.

Lesson #3. Flexibility and adaptability for risk management, identification and mitigation

Just like any other project, the ability to be flexible and adaptable is essential. The project management team quickly realized these skills were especially important in the early stages of the design and construction sequencing when dealing with delivery and supply chain impacts. The team also learned the importance of interdisciplinary cohesion and how to balance solutions with boundary limits of design integrations.

INVESTING IN GREEN ENERGY PROJECTS

In alignment with the City of Edmonton’s objectives, its Waste Services branch is focused on leveraging its resources while reducing its carbon footprint and has invested in a variety of projects that complement the future RNG generation facility.

REFUSE-DERIVED FUEL FACILITY

At Edmonton’s Refuse Derived Fuel plant, garbage is processed and turned into refuse-derived fuel (RDF), or “garbage fluff.” Making RDF involves: mechanically separating municipal solid waste that cannot be recycled or composted; removing inert contaminants; removing precious metals that can be recycled; shredding remaining waste into approximately 40-mm pieces; and drying the shredded waste.

The City’s expertise in developing RDF has potential applications in various waste-to-energy processes.

The City recently entered into an agreement with Varme Energy to generate green electricity and industrial heat while enabling the diversion of at least 150,000 tonnes of residential garbage from landfill per year beginning as early as 2027.

This type of waste-to-energy facility combusts garbage to produce steam that either generates electricity or provides heat for industrial processes.

This facility will complement the work done at the Edmonton Waste Management Centre to sort and process residential waste. By putting residual garbage to use as a fuel source, the City can keep more waste out of the landfill and contribute to Edmonton’s green energy transition. •

The information in this project snapshot has been provided by project stakeholders, partners and managers to educate the public and municipalities about the benefits of RNG production. More Project Snapshots can be found at: www.municipalbiogas.ca/projects.

©Annex Biomass_CFI_OF. View All Articles.

Converting landfill gas to RNG in Edmonton
https://magazine.canadianbiomassmagazine.ca/article/Converting+landfill+gas+to+RNG+in+Edmonton/4825393/827715/article.html

Menu
  • Page View
  • Contents View
  • Advertisers

Issue List

Summer 2025

Spring 2025

Winter 2025

Fall 2024

Summer 2024

Spring 2024

Winter 2024

Fall 2023

Summer 2023

Spring 2023

Winter 2023

Fall 2022

Summer 2022

Spring 2022

Winter 2022

Fall 2021

Summer 2021

Spring 2021

Winter 2021

Fall 2020

Summer 2020

Spring 2020

Winter 2020

Fall 2019

Summer 2019

Spring 2019

Winter 2019

September-October 2018

JulyAugust 2018

MayJune 2018

March April 2018

January-February 2018

November/December 2017

September/October 2017

July/August 2017

May-June 2017

March-April 2017

January February 2017

November December 2016

October 2016

July August 2016

June 2016

March April 2016

January February 2016

November/December 2015

September/October 2015

July August 2015

May-June 2015

March-April 2015

January-February 2015

November - December 2014

September October 2014

Intersaw Guide 2014

July August 2014

May June 2014

March/April 2014

January/February 2014

November/December 2013

September/October 2013

August/September 2013

May/June 2013

March/April 2013

January/February 2013

November/December 2012

September/October 2012

July/August 2012

May/June 2012

March/April 2012

January/February 2012

November/December 2011

September/October 2011

July/August 2011

May/June 2011

April 2011

January/February 2011

November/December 2010

September/October 2010

July/August 2010

May/June 2010

March/April 2010

January/February 2010

November/December 2009

September/October 2009

August 2009

June 2009

March 2009

December 2008

August 08


Library