Canadian Biomass - November/December 2017

Green Operations

Andrew Snook 2017-12-04 03:01:12

Town of Riverview opts for biomass-fuelled operations centre

In 2013, the Town of Riverview, a suburb of Moncton, N.B., had a workspace problem. The town’s public works garage needed to be replaced with a larger, more functional workspace for the town’s Department of Engineering and Department of Public Works and Parks.

The town identified the need for the new facility in its 2013 Strategic Planning process and was able to approve the $16.6 million needed for the construction of the new facility in its budget in 2015.

In August 2015, the town broke ground on the construction of the new 57,535-sq.-ft. facility. In the fall of 2016, construction on the new Riverview Operations Centre was complete, which included administration space for municipal staff – which can be upwards of 62 people, depending on the time of year – and storage for the Parks and Facilities’ vehicle and equipment fleet.

In addition to the main building, the project included the construction of an 11,744-sq.-ft. salt and sand shed, and an 8,159-sq.-ft. cold storage building for construction materials. Foulem Construction was awarded the contract to build the facility.

GREEN HEATING

The town had a variety of energy options but was interested in green energy solutions. During the design phase with Exp Engineering, the prime building consultant, a lease-to-own energy arrangement was determined to offer the best overall solution. The town was able to exclude the boiler system from their cost, forgo the operation, maintenance and long term liability of the heating plant, and pay metered energy price more than competitive to other fuel sources. The lease to own arrangement provided a wide range of flexible alternatives for the future.

The energy lease tender encouraged local interest, from mechanical contractors, energy suppliers, and engineering organizations. Design Built Mechanical of Charlo, N.B. submitted the winning tender, together with their engineering partner, MCW.

The design included a biomass- fuelled system with a Viessmann Pyrot 300 wood-fired boiler (300kW) to heat the facilities. The Pyrot 300 produces a maximum water temperature of 250F, a maximum water pressure of 30 psig, and is fuelled by locally-sourced wood chips that are supplied by ACFOR, a local forest restoration and energy company based in Cocagne, N.B. ACFOR provided locally sourced fuel as part of their forest management agreement with local partners.

Design Built Mechanical provided a self-contained mechanical plant including the boiler, fuel storage, buffer tank, heat exchangers, pumps and other ancillary equipment for a complete heating system just outside of the main operations centre. An integrated control panel monitors and controls the heating plant and measures/calculates the monthly energy consumption.

“Everything was manufactured at their site then connected on site,” explains Daron Thomas, president of Thomas Industrial Sales. “They laid it all out in 3D AutoCAD. The building was built around the system, delivered to sight, and connected to the mechanical services in the operations building. Underground insulated PEX pipe delivers hot water to the mechanical system.”

The biomass system was completed with a 40-ton wood chip storage building, offering weeks of peak load operation in the winter. The delivered wood chips, with moisture content below 15 per cent, provide the Town of Riverview with renewable energy. Much of the fuel is sourced locally from an area surrounding the town’s water supply.

An electric boiler and small holding tank provide back up energy for the building. The boiler plant is matched to the main building and, besides the stainless steel chimney, looks like a storage building

“The fuel provider has several similar operating systems in P.E.I., and brought a lot of knowledge to the table,” Thomas says. “ACFOR is a forward-thinking partner, who we hope to engage in the future on similar projects.”

To optimize the boiler’s efficiency, Thomas Industrial Sales also installed a 6,000-litre buffer tank to allow for extended run times. The hot water from the buffer tank is then pumped via two Armstrong variable speed pumps at a flow rate up to 120 Usgpm into the distribution system in the building’s mechanical system. The heating system includes fan style heaters, radiation floor heating, and conventional hot water heaters. Control of the system, not just the boiler, is paramount.

Cameras have also been installed in several areas inside the boiler room to help Design Build keep a close eye on the system to ensure it’s operating efficiently. The owner pays for heat they purchase only, so smooth operation and reliability are key.

The biomass system is owned by Design-Built Mechanical with an extended contract in place to supply energy to the Riverview Operations Centre, allowing the town to reduce its expenses related to the construction of the operations centre, while ensuring a long-term, low-cost energy supply and supporting local businesses.

“They’re turning waste into low energy fuel,” Thomas says.

“It makes perfect sense for everyone. The municipality wins, the industry wins, and the environment wins.”

©Annex Biomass_CFI_OF. View All Articles.

Green Operations
https://magazine.canadianbiomassmagazine.ca/article/Green+Operations/2953910/458689/article.html

Menu
  • Page View
  • Contents View
  • Advertisers

Issue List

Summer 2025

Spring 2025

Winter 2025

Fall 2024

Summer 2024

Spring 2024

Winter 2024

Fall 2023

Summer 2023

Spring 2023

Winter 2023

Fall 2022

Summer 2022

Spring 2022

Winter 2022

Fall 2021

Summer 2021

Spring 2021

Winter 2021

Fall 2020

Summer 2020

Spring 2020

Winter 2020

Fall 2019

Summer 2019

Spring 2019

Winter 2019

September-October 2018

JulyAugust 2018

MayJune 2018

March April 2018

January-February 2018

November/December 2017

September/October 2017

July/August 2017

May-June 2017

March-April 2017

January February 2017

November December 2016

October 2016

July August 2016

June 2016

March April 2016

January February 2016

November/December 2015

September/October 2015

July August 2015

May-June 2015

March-April 2015

January-February 2015

November - December 2014

September October 2014

Intersaw Guide 2014

July August 2014

May June 2014

March/April 2014

January/February 2014

November/December 2013

September/October 2013

August/September 2013

May/June 2013

March/April 2013

January/February 2013

November/December 2012

September/October 2012

July/August 2012

May/June 2012

March/April 2012

January/February 2012

November/December 2011

September/October 2011

July/August 2011

May/June 2011

April 2011

January/February 2011

November/December 2010

September/October 2010

July/August 2010

May/June 2010

March/April 2010

January/February 2010

November/December 2009

September/October 2009

August 2009

June 2009

March 2009

December 2008

August 08


Library